Separate scope change from overrun

About 18 minutes · 4 reading + 14 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A reconciled project cost sheet showing baseline, incurred costs, open commitments, forecast to finish, and a supported change recommendation.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • An approved-scope baseline with checked quantities and costs.
  • A cost register with three non-overlapping categories.
  • A price-variance note with invoice and full-project effects.
  • A forecast-to-finish sheet and two-cause variance explanation.
  • A scope-change request separating incremental work and existing variance.
  • A final reconciled cost-control packet with versions, causes and next decision.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Every required section is present and traceable to the supplied case facts.
  • Decisions separate known facts, assumptions, and unresolved questions.
  • Records, calculations, and instructions agree with each other and the stated rules.
  • The final revision addresses a changed case and explains what someone should do next.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Current approved scope 100 kits, B1 $800; forecast for that scope $890. Proposed addition: 10 more kits at $3.30 materials and $4 assembly each, no extra delivery. Added scope is not yet approved. Lee must decide. Existing $90 overrun remains separate from the added-scope estimate.

The idea

More approved work and higher cost for existing work are different decisions.

Follow along

Separate scope change from overrun — guided practice

Prepare a change request without hiding an existing variance.

Use a text editor, a free document editor, or paper. Start from the following fictional records; they reset this lesson even if your earlier answer differed. Current approved scope 100 kits, B1 $800; forecast for that scope $890. Proposed addition: 10 more kits at $3.30 materials and $4 assembly each, no extra delivery. Added scope is not yet approved. Lee must decide. Existing $90 overrun remains separate from the added-scope estimate.

  1. 1. Estimate the addition

    Calculate materials and assembly for 10 extra kits.

    You should see: $33 + $40 = $73.

    The request should price the proposed additional work.

  2. 2. Show the existing gap

    Retain the $90 variance for the original scope.

    You should see: $890 forecast versus $800 baseline.

    A scope request should not conceal an unrelated overrun.

  3. 3. Calculate conditional forecast

    Add $73 to the current forecast if the addition is approved.

    You should see: $963 for 110 kits.

    The estimate makes the decision’s total consequence visible.

  4. 4. Draft the request

    State scope, incremental cost, total forecast and approval status.

    You should see: 10 extra kits, +$73, conditional forecast $963; pending Lee.

    A request is not an approved baseline revision.

Now change one thing

Proposed addition changes to 20 kits at $3.30 plus $4 per kit, no extra delivery. Enter incremental cost.

Your work

What to finish

A scope-change request separating incremental work and existing variance.

Common mistake

Watch for this

Resetting the baseline to the forecast and calling the overrun solved.

How can I tell I understand it?

Check your result against the worked example, then explain the changed case without using an unstated assumption.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1Original scope is forecast $50 over plan. A new requested feature costs $80. What should the request show?
2A manager has not approved a $200 change request. What should the baseline do?
3A project forecast is $900 and proposed extra work is $75. What is the conditional new forecast?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
5
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Optional course overview video · same video as Lesson 1
EdspiraStandard Costs and Variance AnalysisYouTube
Optional course overview

Standard Costs and Variance Analysis

From Edspira. Watch here or open it on YouTube .

Optional course overview. Follow the written steps below at your own pace.
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

GAO Cost Estimating and Assessment Guide
Source & access notes · checked 2026-09-12

Inspected March 2020 guide overview: scope, assumptions, documentation and updating estimates with actual costs. Public federal guidance; original small-project case is not an agency procedure.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

NASA documenting cost-estimate results
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix H, especially basis of estimate, input assumptions, traceability and presentation of cost drivers.

Access: Public six-page agency PDF; no account.

Reuse: Reference link only. No text, charts, templates or third-party material reproduced.

NASA using performance information to adjust estimates
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix I on using performance information to update estimates.

Access: Public agency PDF; no account.

Reuse: Reference link only. Course records and arithmetic are independently authored.

Report a problem with this lesson

Tell us what went wrong. Please leave out personal information and private project contents.

No sign-in needed.