Course Library · Lesson 1 of 6
Work · Guided lesson

Read the cost baseline

About 18 minutes · 4 reading + 14 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A reconciled project cost sheet showing baseline, incurred costs, open commitments, forecast to finish, and a supported change recommendation.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • An approved-scope baseline with checked quantities and costs.
  • A cost register with three non-overlapping categories.
  • A price-variance note with invoice and full-project effects.
  • A forecast-to-finish sheet and two-cause variance explanation.
  • A scope-change request separating incremental work and existing variance.
  • A final reconciled cost-control packet with versions, causes and next decision.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Every required section is present and traceable to the supplied case facts.
  • Decisions separate known facts, assumptions, and unresolved questions.
  • Records, calculations, and instructions agree with each other and the stated rules.
  • The final revision addresses a changed case and explains what someone should do next.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Fictional North Room welcome-kit project: 100 kits. Approved plan: materials $3 per kit, assembly $4 per kit, one delivery $100. No tax or other fees in this exercise. Baseline version B1 is approved at $800. A separate $50 organizational reserve is not authorized for this project and must not be added to its baseline.

The idea

A baseline describes both the work and its planned cost.

Follow along

Read the cost baseline — guided practice

Build a checked baseline for an approved quantity.

Use a text editor, a free document editor, or paper. Start from the following fictional records; they reset this lesson even if your earlier answer differed. Fictional North Room welcome-kit project: 100 kits. Approved plan: materials $3 per kit, assembly $4 per kit, one delivery $100. No tax or other fees in this exercise. Baseline version B1 is approved at $800. A separate $50 organizational reserve is not authorized for this project and must not be added to its baseline.

  1. 1. Name scope

    Record 100 kits and baseline B1.

    You should see: Every planned unit cost refers to the same 100 kits.

    Scope makes later comparisons meaningful.

  2. 2. Extend unit costs

    Multiply materials and labor rates by quantity.

    You should see: Materials $300; labor $400.

    Rates alone are not project totals.

  3. 3. Add fixed cost

    Add the one $100 delivery.

    You should see: Total $800.

    A fixed charge is counted once.

  4. 4. Keep reserve separate

    Note that $50 is outside current authorization.

    You should see: Approved baseline stays $800.

    Available organizational money is not automatic project permission.

Now change one thing

Changed plan is 120 kits at $3 materials and $4 labor each, plus one $100 delivery. Enter total planned cost.

Your work

What to finish

An approved-scope baseline with checked quantities and costs.

Common mistake

Watch for this

Changing the comparison baseline merely because a forecast rises.

How can I tell I understand it?

Check your result against the worked example, then explain the changed case without using an unstated assumption.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1A project plans 50 items at $6 each plus one $40 delivery. What is the baseline total?
2A budget says $1,000 but does not state the quantity or scope. Which information explains what the $1,000 is intended to buy?
3A separate reserve exists but has not been authorized for the project. What should the current baseline show?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
1
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Optional course overview video
EdspiraStandard Costs and Variance AnalysisYouTube
Optional course overview

Standard Costs and Variance Analysis

From Edspira. Watch here or open it on YouTube .

Optional course overview. Follow the written steps below at your own pace.
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

GAO Cost Estimating and Assessment Guide
Source & access notes · checked 2026-09-12

Inspected March 2020 guide overview: scope, assumptions, documentation and updating estimates with actual costs. Public federal guidance; original small-project case is not an agency procedure.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

NASA documenting cost-estimate results
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix H, especially basis of estimate, input assumptions, traceability and presentation of cost drivers.

Access: Public six-page agency PDF; no account.

Reuse: Reference link only. No text, charts, templates or third-party material reproduced.

NASA using performance information to adjust estimates
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix I on using performance information to update estimates.

Access: Public agency PDF; no account.

Reuse: Reference link only. Course records and arithmetic are independently authored.

Standard Costs and Variance Analysis
Source & access notes · checked 2026-09-12

Search located the exact watch URL; YouTube oEmbed verified title and Edspira channel. Accounting instructor introduction to comparing actual and expected costs. Metadata and source were checked on 2026-09-12; full playback was not tested.

Access: Public YouTube metadata verified; viewing may depend on region/network. Optional; every activity works from written material.

Reuse: Link or embed only. No video download, transcription, or rehosting.

Report a problem with this lesson

Tell us what went wrong. Please leave out personal information and private project contents.

No sign-in needed.