Explain a unit-price change

About 18 minutes · 4 reading + 14 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A reconciled project cost sheet showing baseline, incurred costs, open commitments, forecast to finish, and a supported change recommendation.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • An approved-scope baseline with checked quantities and costs.
  • A cost register with three non-overlapping categories.
  • A price-variance note with invoice and full-project effects.
  • A forecast-to-finish sheet and two-cause variance explanation.
  • A scope-change request separating incremental work and existing variance.
  • A final reconciled cost-control packet with versions, causes and next decision.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Every required section is present and traceable to the supplied case facts.
  • Decisions separate known facts, assumptions, and unresolved questions.
  • Records, calculations, and instructions agree with each other and the stated rules.
  • The final revision addresses a changed case and explains what someone should do next.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Materials price is now $3.30 for the same 100 kits, replacing the planned $3. Sixty kits’ materials are received: $198 instead of planned $180. The remaining 40 kits cost $132. Assembly still totals $400 and delivery $100. No extra kit quantity is approved.

The idea

Separate the price per unit from the number of units.

Follow along

Explain a unit-price change — guided practice

Trace a cost variance to a changed assumption.

Use a text editor, a free document editor, or paper. Start from the following fictional records; they reset this lesson even if your earlier answer differed. Materials price is now $3.30 for the same 100 kits, replacing the planned $3. Sixty kits’ materials are received: $198 instead of planned $180. The remaining 40 kits cost $132. Assembly still totals $400 and delivery $100. No extra kit quantity is approved.

  1. 1. Check received materials

    Multiply 60 by actual $3.30.

    You should see: $198 received materials.

    The invoice can be checked against quantity and rate.

  2. 2. Check remaining materials

    Multiply 40 by $3.30.

    You should see: $132 remaining materials.

    Forecast must use the changed rate for future units too.

  3. 3. Compare full materials cost

    Compare $330 forecast with $300 baseline.

    You should see: $30 over plan from price change.

    A partial invoice variance is not the whole-project effect.

  4. 4. Rebuild project forecast

    Add materials $330, assembly $400 and delivery $100.

    You should see: $830 forecast, $30 above baseline.

    The explanation links the assumption change to the project total.

Now change one thing

Changed price is $3.20 for all 100 kits, with baseline price $3. Enter the materials cost increase.

Your work

What to finish

A price-variance note with invoice and full-project effects.

Common mistake

Watch for this

Calling a price increase a quantity overrun when the kit count is unchanged.

How can I tell I understand it?

Check your result against the worked example, then explain the changed case without using an unstated assumption.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1A team still needs 80 units, but price rises from $5 to $5.50. What is the added cost?
2Price stays $2 per item, but quantity rises from 100 to 110. What caused the $20 increase?
3Only 20 of 100 units have been bought at a new higher price that also applies to the remaining 80. What should the forecast include?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
3
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Optional course overview video · same video as Lesson 1
EdspiraStandard Costs and Variance AnalysisYouTube
Optional course overview

Standard Costs and Variance Analysis

From Edspira. Watch here or open it on YouTube .

Optional course overview. Follow the written steps below at your own pace.
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

GAO Cost Estimating and Assessment Guide
Source & access notes · checked 2026-09-12

Inspected March 2020 guide overview: scope, assumptions, documentation and updating estimates with actual costs. Public federal guidance; original small-project case is not an agency procedure.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

NASA documenting cost-estimate results
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix H, especially basis of estimate, input assumptions, traceability and presentation of cost drivers.

Access: Public six-page agency PDF; no account.

Reuse: Reference link only. No text, charts, templates or third-party material reproduced.

NASA using performance information to adjust estimates
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix I on using performance information to update estimates.

Access: Public agency PDF; no account.

Reuse: Reference link only. Course records and arithmetic are independently authored.