Publish the cost-control brief

About 18 minutes · 4 reading + 14 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A reconciled project cost sheet showing baseline, incurred costs, open commitments, forecast to finish, and a supported change recommendation.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • An approved-scope baseline with checked quantities and costs.
  • A cost register with three non-overlapping categories.
  • A price-variance note with invoice and full-project effects.
  • A forecast-to-finish sheet and two-cause variance explanation.
  • A scope-change request separating incremental work and existing variance.
  • A final reconciled cost-control packet with versions, causes and next decision.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Every required section is present and traceable to the supplied case facts.
  • Decisions separate known facts, assumptions, and unresolved questions.
  • Records, calculations, and instructions agree with each other and the stated rules.
  • The final revision addresses a changed case and explains what someone should do next.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Lee approves the 10-kit addition at $73. Revised scope 110 kits; baseline B2 is $873 ($800+$73). Current forecast remains $963. Incurred costs still $358. The $73 addition is entirely future work. Current forecast-to-finish is therefore $605. Lee requests a review of assembly options; no savings are confirmed.

The idea

Approval of extra scope does not erase overruns on the original scope.

Follow along

Publish the cost-control brief — guided practice

Reconcile an approved scope revision and preserve the remaining variance.

Use a text editor, a free document editor, or paper. Start from the following fictional records; they reset this lesson even if your earlier answer differed. Lee approves the 10-kit addition at $73. Revised scope 110 kits; baseline B2 is $873 ($800+$73). Current forecast remains $963. Incurred costs still $358. The $73 addition is entirely future work. Current forecast-to-finish is therefore $605. Lee requests a review of assembly options; no savings are confirmed.

  1. 1. Record the new baseline

    Write B2, scope 110 and approved amount.

    You should see: $873 baseline, approval recorded.

    The revision changes only the authorized addition.

  2. 2. Compare forecast and baseline

    Subtract $873 from $963.

    You should see: $90 forecast overrun remains.

    The original scope variance has not disappeared.

  3. 3. Reconcile to-finish amount

    Subtract incurred $358 from final forecast.

    You should see: $605 remains forecast to finish.

    This checks that total and remaining costs agree.

  4. 4. Write a decision brief

    State baseline, actual, forecast, variance, causes and next review owner.

    You should see: Lee reviews assembly options; no unverified saving is booked.

    The report should support a decision without inventing its result.

Now change one thing

A confirmed change lowers final forecast from $963 to $943 while baseline stays $873. Enter remaining forecast overrun.

Your work

What to finish

A final reconciled cost-control packet with versions, causes and next decision.

Common mistake

Watch for this

Treating a hoped-for cost reduction as a confirmed saving.

How can I tell I understand it?

Check your result against the worked example, then explain the changed case without using an unstated assumption.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1Revised approved budget is $1,200 and forecast is $1,280. What is the forecast overrun?
2A proposed saving of $60 has no agreed method or evidence yet. How should it appear?
3Actual cost is $450 and forecast remaining is $350. A report says final forecast $700. What needs correction?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
6
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Optional course overview video · same video as Lesson 1
EdspiraStandard Costs and Variance AnalysisYouTube
Optional course overview

Standard Costs and Variance Analysis

From Edspira. Watch here or open it on YouTube .

Optional course overview. Follow the written steps below at your own pace.
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

GAO Cost Estimating and Assessment Guide
Source & access notes · checked 2026-09-12

Inspected March 2020 guide overview: scope, assumptions, documentation and updating estimates with actual costs. Public federal guidance; original small-project case is not an agency procedure.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

NASA documenting cost-estimate results
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix H, especially basis of estimate, input assumptions, traceability and presentation of cost drivers.

Access: Public six-page agency PDF; no account.

Reuse: Reference link only. No text, charts, templates or third-party material reproduced.

NASA using performance information to adjust estimates
Source & access notes · checked 2026-09-12

Inspected February 2015 Appendix I on using performance information to update estimates.

Access: Public agency PDF; no account.

Reuse: Reference link only. Course records and arithmetic are independently authored.

Report a problem with this lesson