Respond to a disruption

About 19 minutes · 4 reading + 15 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A run of show, staffing map, access checklist, and disruption log for a fictional indoor careers showcase.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • A constraint card with times, capacity and decision owners.
  • A timed run of show with segment and cue owners.
  • A coverage grid and two-part handoff script.
  • An access check and clear escalation message.
  • A revised run of show and communication log.
  • A complete operations packet and evidence-based debrief.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Every required section is present and traceable to the supplied case facts.
  • Decisions separate known facts, assumptions, and unresolved questions.
  • Records, calculations, and instructions agree with each other and the stated rules.
  • The final revision addresses a changed case and explains what someone should do next.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Original program ends 15:00. At 13:20 the final demo speaker reports they will be ready at 14:00 instead of 13:50. Their demo still needs 20 minutes. Lee approves: use 13:50–14:00 for a break, demo 14:00–14:20, questions 14:20–14:50, close 14:50–15:00. Mo and Sam need the revised cues. Version changes from 1 to 2.

The idea

A useful contingency changes the plan and makes the new plan visible.

Follow along

Respond to a disruption — guided practice

Revise a program within fixed limits and communicate one current version.

Use a text editor, a free document editor, or paper. Start from the following fictional records; they reset this lesson even if your earlier answer differed. Original program ends 15:00. At 13:20 the final demo speaker reports they will be ready at 14:00 instead of 13:50. Their demo still needs 20 minutes. Lee approves: use 13:50–14:00 for a break, demo 14:00–14:20, questions 14:20–14:50, close 14:50–15:00. Mo and Sam need the revised cues. Version changes from 1 to 2.

  1. 1. Identify what moves

    Locate the late demo and the flexible break.

    You should see: The break moves before the last demo.

    Reordering can preserve duration without overrunning.

  2. 2. Check the finish

    Add all revised end segments.

    You should see: Demo ends 14:20; questions and close still finish 15:00.

    A change must fit every fixed boundary.

  3. 3. Issue revision 2

    Write the changed times, approval and current version.

    You should see: Version 2, approved Lee, replaces version 1 for affected cues.

    One current plan limits contradictory instructions.

  4. 4. Confirm key receivers

    Draft Mo and Sam acknowledgements of their changed cues.

    You should see: Mo prepares audio at 14:00; Sam guides break at 13:50.

    A revised file is useful only if affected people know it changed.

Now change one thing

A speaker begins at 14:05 and needs 20 minutes. Enter their finish in HH:MM format.

Your work

What to finish

A revised run of show and communication log.

Common mistake

Watch for this

Solving a delay by silently extending the fixed finish.

How can I tell I understand it?

Check your result against the worked example, then explain the changed case without using an unstated assumption.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1A hard 16:00 finish remains, but a segment now ends 15:50 and closing needs 15 minutes. What is true?
2A changed schedule is sent only to the host, while audio and floor staff retain old cues. What is missing?
3A staff member proposes swapping two sessions to absorb a delay. What should be checked before approval?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
5
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Optional course overview video · same video as Lesson 1
Ashlee TateHow To Plan Your First Event Successfully | Event Planning TipsYouTube
Optional course overview

How To Plan Your First Event Successfully | Event Planning Tips

From Ashlee Tate. Watch here or open it on YouTube .

Optional course overview. Follow the written steps below at your own pace.
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

HSE running an event
Source & access notes · checked 2026-09-12

Inspected planning, management and after-event guidance; UK context.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

HSE managing an event
Source & access notes · checked 2026-09-12

Inspected coordination, communication, monitoring and review.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

HSE incidents and emergencies
Source & access notes · checked 2026-09-12

Inspected contingency planning, named responsibilities and testing; no technical emergency actions are assigned here.

Access: Public page inspected without an account.

Reuse: Reference link only. Course prose and practice data are original; no third-party text, figures, or templates are reproduced.

Report a problem with this lesson

Tell us what went wrong. Please leave out personal information and private project contents.

No sign-in needed.