Offset lead times from the required assembly date
See this course’s project requirements
A two-level paper bill-of-materials explosion, net material requirement sheet, batch release decision and revised production packet for fictional stationery kits.
Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.
What to include
- Save a v1 gross-material explosion grouped by component; include the original-case decision evidence and a separate changed-case result.
- Net loose stock and save the dependency calculation; include the original-case decision evidence and a separate changed-case result.
- Write a Day3 shortage register with excluded supply reasons; include the original-case decision evidence and a separate changed-case result.
- Save the dated dependency schedule and late-order flag; include the original-case decision evidence and a separate changed-case result.
- Save the v2 shortage with EC2 link and superseded v1 value; include the original-case decision evidence and a separate changed-case result.
- Assemble the versioned manufacturing-planning packet; include the original-case decision evidence and a separate changed-case result.
Review and revise
Use these criteria to check your work and choose what to improve.
- The final packet uses the supplied task-specific constraints and all six records agree.
- Every result can be traced to an identifier, input, calculation or stated decision rule.
- Changed-case practice updates dependent records and keeps holds or uncertainty visible.
- The packet states the learner role, authority boundary and specific next verification needed before real work.
Want more background?
The idea in everyday life
Original fictional workplace practice; paper or a local document is sufficient. The rules and records below are supplied for this exercise, not asserted universal workplace policy. Spruce final assembly K takes 1 planning day and must finish Day8. A takes 2 days and T takes 1 day, both needed at final assembly start. Loose C procurement lead time is 3 days and P is 2 days; both needed when A starts. Exercise convention: start day plus duration equals finish day; no weekends.
Backward scheduling subtracts supplied lead times along dependencies; it does not make a late receipt timely merely by changing a calendar label.
Offset lead times from the required assembly date — worked practice
Backward scheduling subtracts supplied lead times along dependencies; it does not make a late receipt timely merely by changing a calendar label.
Spruce final assembly K takes 1 planning day and must finish Day8. A takes 2 days and T takes 1 day, both needed at final assembly start. Loose C procurement lead time is 3 days and P is 2 days; both needed when A starts. Exercise convention: start day plus duration equals finish day; no weekends. Use paper or a local document. Preserve the original case and make a separate changed-case record.
1. Step 1
Subtract final assembly duration from Day8.
You should see: K begins Day7; A/T must be ready Day7.
Keep the stated identifier, unit and policy alongside this result so another reader can check it.
2. Step 2
Offset A and T durations independently.
You should see: A begins Day5; T begins Day6.
Keep the stated identifier, unit and policy alongside this result so another reader can check it.
3. Step 3
Offset component procurement for the earlier A need.
You should see: C order by Day2; P by Day3 for arrival Day5.
Keep the stated identifier, unit and policy alongside this result so another reader can check it.
4. Step 4
Save the dated dependency schedule and late-order flag.
You should see: A schedule linking Day2 C/Day3 P orders, Day5 A, Day6 T and Day7 K start.
Keep the stated identifier, unit and policy alongside this result so another reader can check it.
What to finish
Save the dated dependency schedule and late-order flag; include the original-case decision evidence and a separate changed-case result.
Watch for this
Scheduling each material against final completion instead of its own earlier dependent start.
How can I tell I understand it?
Using the supplied identifiers, I can save the dated dependency schedule and late-order flag. My changed-case record names the revised condition and explains which dependent decision it changes.
Quick knowledge check
Answer all 3 questions. Get at least 2 right and the lesson completes automatically.
You’ll get an explanation for each answer. Signed in? Your results save to your account.
Pass the check. We’ll save the progress.
Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.
Go to the knowledge checkTools, templates, and lesson sources
Tools and templates
Tools open in a new tab so you can keep your place here.
Sources and further reading
Explore the references behind this lesson.
Source & access notes · checked 2026-10-01
Occupational task and responsibility context; the exercise policies and quantities are original fictional inputs. Page title and relevant content inspected; no interactive controls or credential process tested.
Access: Readable official page retrieved with the web reader on 2026-10-01.
Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.
Source & access notes · checked 2026-10-01
Public agency or educational context; no source exercises are copied and no simulated threshold is presented as an official rule. The direct-access limitation is preserved; official search-retrieved context supports the stated scope only.
Access: Official primary-page summary was available in web search; direct page retrieval was blocked in this environment. Full page and interactive operation are not claimed.
Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.
Source & access notes · checked 2026-10-01
Public agency or educational context; no source exercises are copied and no simulated threshold is presented as an official rule. The direct-access limitation is preserved; official search-retrieved context supports the stated scope only.
Access: Official primary-page summary was available in web search; direct page retrieval was blocked in this environment. Full page and interactive operation are not claimed.
Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.
Report a problem with this lesson
Tell us what went wrong. Please leave out personal information and private project contents.