Compare two feasible route assignments

About 11 minutes · 3 reading + 8 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A tested two-worker dispatch plan using supplied travel times, skill matches, appointment windows and breaks, plus a disruption revision and customer-update log.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • Build a constraint matrix before allocating routes; include the original-case decision evidence and a separate changed-case result.
  • Add J3 and return travel for full route end; include the original-case decision evidence and a separate changed-case result.
  • Save the paired assignment with all checks visible; include the original-case decision evidence and a separate changed-case result.
  • Recommend from comparable evidence and note the 10-minute assumption gap; include the original-case decision evidence and a separate changed-case result.
  • Draft a revised dispatch/customer update with the changed times; include the original-case decision evidence and a separate changed-case result.
  • Assemble dispatch packet and next verification action; include the original-case decision evidence and a separate changed-case result.

Review and revise

Use these criteria to check your work and choose what to improve.

  • The final packet uses the supplied task-specific constraints and all six records agree.
  • Every result can be traced to an identifier, input, calculation or stated decision rule.
  • Changed-case practice updates dependent records and keeps holds or uncertainty visible.
  • The packet states the learner role, authority boundary and specific next verification needed before real work.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Original fictional workplace practice; paper or a local document is sufficient. The rules and records below are supplied for this exercise, not asserted universal workplace policy. Oak Plan A: N handles J1/J3 route 140 min; M handles J2 route 60 min, total 200. Plan B: M handles J1/J3 route 140; N does not have Y and J2 is left unassigned. Proposed claim: Plan B uses only 140 minutes and is better.

The idea

Comparing routes requires the same complete jobs and accounted travel; an apparently shorter plan that omits a job is not a fair comparison.

Follow along

Compare two feasible route assignments — worked practice

Comparing routes requires the same complete jobs and accounted travel; an apparently shorter plan that omits a job is not a fair comparison.

Oak Plan A: N handles J1/J3 route 140 min; M handles J2 route 60 min, total 200. Plan B: M handles J1/J3 route 140; N does not have Y and J2 is left unassigned. Proposed claim: Plan B uses only 140 minutes and is better. Use paper or a local document. Preserve the original case and make a separate changed-case record.

  1. 1. Step 1

    Check coverage before comparing times.

    You should see: Plan A covers 3 jobs; Plan B covers 2 and misses J2.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  2. 2. Step 2

    Separate feasibility from objective value.

    You should see: Plan B is not a complete feasible alternative.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  3. 3. Step 3

    Use a second complete hypothetical Plan C for comparison.

    You should see: Supplied Plan C covers three jobs in 210 minutes with all skills/windows checked.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  4. 4. Step 4

    Recommend from comparable evidence and note the 10-minute assumption gap.

    You should see: A route comparison favoring Plan A at 200 minutes over verified Plan C at 210 minutes while excluding incomplete Plan B.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

Now change one thing

New validated Plan D covers all three jobs in 195 minutes with same conditions. How many minutes less is D than A?

Your work

What to finish

Recommend from comparable evidence and note the 10-minute assumption gap; include the original-case decision evidence and a separate changed-case result.

Common mistake

Watch for this

Choosing a low route-time total that quietly leaves required work undone.

How can I tell I understand it?

Using the supplied identifiers, I can recommend from comparable evidence and note the 10-minute assumption gap. My changed-case record names the revised condition and explains which dependent decision it changes.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1Oak Plan B uses 140 minutes but leaves J2 unassigned. Can it be compared as a complete alternative?
2Oak complete Plan A: 200 and complete Plan C: 210 meet all constraints. Difference?
3What does Oak’s Plan A comparison establish?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
4
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

43-5032.00 - Dispatchers, Except Police, Fire, and Ambulance
Source & access notes · checked 2026-10-01

Occupational task and responsibility context; the exercise policies and quantities are original fictional inputs. Page title and relevant content inspected; no interactive controls or credential process tested.

Access: Readable official page retrieved with the web reader on 2026-10-01.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

43-5061.00 - Production, Planning, and Expediting Clerks
Source & access notes · checked 2026-10-01

Occupational task and responsibility context; the exercise policies and quantities are original fictional inputs. Page title and relevant content inspected; no interactive controls or credential process tested.

Access: Readable official page retrieved with the web reader on 2026-10-01.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

moodle.skills commons.org — view.php?id=46
Source & access notes · checked 2026-10-01

Public agency or educational context; no source exercises are copied and no simulated threshold is presented as an official rule. The direct-access limitation is preserved; official search-retrieved context supports the stated scope only.

Access: Official primary-page summary was available in web search; direct page retrieval was blocked in this environment. Full page and interactive operation are not claimed.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

Report a problem with this lesson

Tell us what went wrong. Please leave out personal information and private project contents.

No sign-in needed.