Carry backlog cohorts forward with FIFO evidence

About 15 minutes · 3 reading + 12 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

A checked fictional four-day service workload model with arrival counts, work-content demand, available capacity, backlog aging, two allocation scenarios and a bounded service-promise recommendation.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • Save queue balance with IDs/cohort state andno assignment-as-completion; include the original-case decision evidence and a separate changed-case result.
  • Save daily/period demand ledger with time-assumption limits; include the original-case decision evidence and a separate changed-case result.
  • Save capacity model with skills/exclusions/whole-job assumptions; include the original-case decision evidence and a separate changed-case result.
  • Save four-day cohort queue with actual modeled served totals; include the original-case decision evidence and a separate changed-case result.
  • Save scenario comparison with bounded service-promise recommendation; include the original-case decision evidence and a separate changed-case result.
  • Save service workload/capacity/FIFO/scenarios/uncertainty project; include the original-case decision evidence and a separate changed-case result.

Review and revise

Use these criteria to check your work and choose what to improve.

  • The final packet uses the supplied task-specific constraints and all six records agree.
  • Every result can be traced to an identifier, input, calculation or stated decision rule.
  • Changed-case practice updates dependent records and keeps holds or uncertainty visible.
  • The packet states the learner role, authority boundary and specific next verification needed before real work.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Original fictional workplace practice; paper or a local document is sufficient. The rules and records below are supplied for this exercise, not asserted universal workplace policy. Cedarbridge opening 4 before Day1, arrivals D1=20, D2=12, D3=25, D4=10; capacity 18/day. FIFO, whole jobs. Serve old jobs before today’s new jobs. No jobs canceled or lost.

The idea

Daily closing work becomes next day opening, and FIFO preserves older cohort identities; same total backlog does not explain its age.

Follow along

Carry backlog cohorts forward with FIFO evidence — worked practice

Daily closing work becomes next day opening, and FIFO preserves older cohort identities; same total backlog does not explain its age.

Cedarbridge opening 4 before Day1, arrivals D1=20, D2=12, D3=25, D4=10; capacity 18/day. FIFO, whole jobs. Serve old jobs before today’s new jobs. No jobs canceled or lost. Use paper or a local document. Preserve the original case and make a separate changed-case record.

  1. 1. Step 1

    Calculate Day1 and Day2 available/served/closing.

    You should see: D124/18/6; D218/18/0.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  2. 2. Step 2

    Calculate Day3 and Day4 including opening carry.

    You should see: D325/18/7; D417/17/0.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  3. 3. Step 3

    Trace older remaining cohorts.

    You should see: D1 remaining 6 cleared D2; D3 remaining 7 cleared D4.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

  4. 4. Step 4

    Save four-day cohort queue with actual modeled served totals.

    You should see: 18+18+18+17=71 served; Day4 one job capacity unused because demand 17.

    Keep the stated identifier, unit and policy alongside this result so another reader can check it.

Now change one thing

Day4 arrivals are 12 instead of10 with 7 opening and 18 capacity. How many jobs close unfinished?

Your work

What to finish

Save four-day cohort queue with actual modeled served totals; include the original-case decision evidence and a separate changed-case result.

Common mistake

Watch for this

Manufacturing completions up to capacity when fewer jobs exist or losing old job cohorts behind a single total.

How can I tell I understand it?

Using the supplied identifiers, I can save four-day cohort queue with actual modeled served totals. My changed-case record names the revised condition and explains which dependent decision it changes.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1Cedarbridge Day2 opens 6 and gets 12 at 18 capacity. Closing backlog?
2Why does Cedarbridge serve 17 rather than 18 on Day4?
3What age cohort makes Cedarbridge Day4 opening 7?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
4
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

43-5032.00 - Dispatchers, Except Police, Fire, and Ambulance
Source & access notes · checked 2026-10-01

Occupational task and responsibility context; the exercise policies and quantities are original fictional inputs. Page title and relevant content inspected; no interactive controls or credential process tested.

Access: Readable official page retrieved with the web reader on 2026-10-01.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

43-5061.00 - Production, Planning, and Expediting Clerks
Source & access notes · checked 2026-10-01

Occupational task and responsibility context; the exercise policies and quantities are original fictional inputs. Page title and relevant content inspected; no interactive controls or credential process tested.

Access: Readable official page retrieved with the web reader on 2026-10-01.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

10.5 Production and Operations Control - Introduction to Business | Open Stax
Source & access notes · checked 2026-10-01

Public agency or educational context; no source exercises are copied and no simulated threshold is presented as an official rule. Page title and relevant content inspected; no interactive controls or credential process tested.

Access: Readable official page retrieved with the web reader on 2026-10-01.

Reuse: All teaching cases, data, worked steps and questions are original. Link and limited paraphrase for context; no copied source exercises.

Report a problem with this lesson

Tell us what went wrong. Please leave out personal information and private project contents.

No sign-in needed.