What to include
- A cost-classification and unit-cost schedule.
- A contribution schedule and two-product profit bridge.
- An overhead-rate and applied-versus-actual reconciliation.
- A capacity feasibility and contribution-per-minute table.
- A checked feasible product mix with an explicit tie and resource ledger.
- A price/capacity sensitivity and conditional product-mix recommendation.
Review and revise
Use these criteria to check your work and choose what to improve.
- Costs: behavior, units and overhead assignment are explicit.
- Feasibility: time/demand/whole-unit constraints hold.
- Objective: contribution and fixed-pool profit reconcile.
- Decision: ties and changed-price/capacity scenarios are checked.
Want more background?
The idea in everyday life
Original fictional practice. All money is USD. No account, payment, personal record or outside participation is required. Fictional workshop sells whole units only. Product A: price 30, variable material 12, variable labor 6, bottleneck 6 min, demand cap 50. Product B: price 24, material 8, labor 4, bottleneck 4 min, demand cap 80. Available bottleneck time 600 min. Monthly fixed manufacturing overhead 600, budget activity 600 min (rate 1/min). All produced units sell within demand limits; no inventory, other constraints or taxes in this bounded model.
A feasible maximum can have more than one equally good mix.
Choose a demand-limited product mix — complete worked case
A feasible maximum can have more than one equally good mix.
Fictional workshop sells whole units only. Product A: price 30, variable material 12, variable labor 6, bottleneck 6 min, demand cap 50. Product B: price 24, material 8, labor 4, bottleneck 4 min, demand cap 80. Available bottleneck time 600 min. Monthly fixed manufacturing overhead 600, budget activity 600 min (rate 1/min). All produced units sell within demand limits; no inventory, other constraints or taxes in this bounded model.
Two products
Paste at A1.
| AProduct | BPrice | CMaterial | DVariable labor | EMachine min | FMax demand |
|---|---|---|---|---|---|
| A | 30 | 12 | 6 | 6 | 50 |
| B | 24 | 8 | 4 | 4 | 80 |
Copy as plain text
1. 5.1 Choose
Allocate B up to its 80 demand cap, then divide remaining 280 min by 6 and round whole A units down.
You should see: 46 A fits;47 A would exceed 600 when B remains 80.
2. 5.2 Choose
Calculate used time, unused time, contribution and overhead-adjusted profit.
You should see: 596 used,4 spare,1,512 contribution,912 profit.
3. 5.3 Choose
Check A-first and the 79 B/47 A alternative explicitly.
You should see: A-first 900 profit;79 B/47 A ties 912.
4. 5.4 Choose
Enumerate A=0 through 50 on paper with B=min(80, floor((600−6×A)/4)), or run the supplied original Python. Keep all maximizing feasible rows, not one falsely unique result.
You should see: The three maxima are (46,80), (47,79) and (48,78), each with 1,512 contribution. Used minutes are 596, 598 and 600 respectively.
What to finish
A checked feasible product mix with an explicit tie and resource ledger.
Watch for this
Rounding up remaining units or calling the first priority plan uniquely optimal.
How can I tell I understand it?
Verify that your completed checked feasible product mix with an explicit tie and resource ledger meets the three lesson-specific checks and retains the supporting original records.
Quick knowledge check
Answer all 3 questions. Get at least 2 right and the lesson completes automatically.
You’ll get an explanation for each answer. Signed in? Your results save to your account.
Pass the check. We’ll save the progress.
Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.
Go to the knowledge checkTools, templates, and lesson sources
Tools and templates
Tools open in a new tab so you can keep your place here.
Sources and further reading
Explore the references behind this lesson.
Source & access notes · checked 2026-10-01
Read unit contribution per scarce resource. This course adds its own whole-unit demand limits and exhaustive small-case comparison.
Access: Public primary page body opened and relevant sections read through the web reader on 2026-10-01; no account required for reading.
Reuse: Original Life Starter cases, datasets and questions; no source exercise or worked dataset reproduced. Links support further reading.
Report a problem with this lesson
Tell us what went wrong. Please leave out personal information and private project contents.