Course Library · Lesson 2 of 6
Work · Guided lesson

Map owners dependencies and due dates

About 11 minutes · 3 reading + 8 practice and checks
Time includes reading, practice, and questions. Extra videos or further study are optional.
See this course’s project requirements

An employer-side onboarding tracker with role-dependent setup, approved access requests, orientation dependencies, missing-item routing and a tested day-one/first-week handoff.

Keep your working files in your own notebook or software. Save a private description, checklist, and work link in My Proof.

What to include

  • A role-setup checklist with private-record routing and explicit exclusions.
  • An onboarding dependency tracker with a feasible access-request sequence.
  • A paper access-request record linked to the role approval.
  • A first-day learning schedule with prerequisite and buffer checks.
  • A missing-item escalation record that preserves approval status.
  • A dated readiness and first-week handoff file with explicit pending items.

Review and revise

Use these criteria to check your work and choose what to improve.

  • Roles, constraints and permissions are preserved and tied to supplied evidence.
  • The original case is worked with visible intermediate decisions and units.
  • Changed cases revise the affected record and preserve unresolved questions.
  • Six lesson outputs form one usable, dated team-operations file with a supported next step.
Open the full course project
Want more background?
Before you begin

The idea in everyday life

Original fictional workplace practice. Use only the supplied people, records, permissions and educational policies; no real employee, applicant, organization or account is required. Five tasks: R supervisor role approval due day −2; D facilities desk ready day −1 independent; A IT folder-access request due day −1 after R; O supervisor-owned orientation day 1 at 09:00 independent of A; P trainer-owned folder practice day 1 at 10:00 after A. Each takes one supplied coordination step; days are relative to arrival.

The idea

A dependency means the successor cannot start until the predecessor’s required output exists. Due dates are targets, not approvals.

Follow along

Map owners dependencies and due dates — worked practice

A dependency means the successor cannot start until the predecessor’s required output exists. Due dates are targets, not approvals.

Use paper or a local document. All people, records, criteria and dates below are invented. Five tasks: R supervisor role approval due day −2; D facilities desk ready day −1 independent; A IT folder-access request due day −1 after R; O supervisor-owned orientation day 1 at 09:00 independent of A; P trainer-owned folder practice day 1 at 10:00 after A. Each takes one supplied coordination step; days are relative to arrival.

Original supplied map owners dependencies and due dates records

Paste at A1.

AIDBOwnerCDueDRequired predecessor
RSupervisorDay −2None
DFacilitiesDay −1None
AITDay −1R approval
OSupervisorDay 1 09:00None
PTrainerDay 1 10:00A completion

Copy as plain text
  1. 1. Step 1: List R, D, A, O and P with their owners and due dates

    List R, D, A, O and P with their owners and due dates.

    You should see: R supervisor; D facilities; A IT; O supervisor; P trainer.

    A dependency means the successor cannot start until the predecessor’s required output exists. Due dates are targets, not approvals.

  2. 2. Step 2: Draw R→A→P and keep D and O as independent branches

    Draw R→A→P and keep D and O as independent branches.

    You should see: Only R approval enables the access request, which enables folder practice.

    Keep this intermediate result so the final decision can be checked.

  3. 3. Step 3: Place R at day −2 and A at day −1; schedule D independently at day −1

    Place R at day −2 and A at day −1; schedule D independently at day −1.

    You should see: The predecessor order meets the supplied dates.

    Keep this intermediate result so the final decision can be checked.

  4. 4. Step 4: Mark each as planned until its named owner supplies completion evidence

    Mark each as planned until its named owner supplies completion evidence.

    You should see: A feasible plan exists, but readiness is not yet verified.

    Keep this intermediate result so the final decision can be checked.

Now change one thing

R approval arrives only on day 1 after the 10:00 practice slot. Type ready or blocked for P under the same dependency.

Your work

What to finish

An onboarding dependency tracker with a feasible access-request sequence.

Common mistake

Watch for this

Treating a due date as proof that the prerequisite approval already exists.

How can I tell I understand it?

Sequence onboarding tasks by owner, predecessor and supplied due date on the supplied changed case while preserving the stated rule and checking the final record.

Try 3 questions

Quick knowledge check

Answer all 3 questions. Get at least 2 right and the lesson completes automatically.

Not yet passed

You’ll get an explanation for each answer. Signed in? Your results save to your account.

1Role approval R is missing, while IT access A requires R. What is A’s status?
2A desk-ready task has no access dependency. May its owner continue while approval is pending?
3What turns the access row from planned into verified ready in this case?
0 of 3 answeredApply the lesson to a short question, then review the explanation.
2
Finish this lesson

Pass the check. We’ll save the progress.

Answer all 3 questions above and get at least 2 right. You can review the explanations and try again.

Go to the knowledge check
Tools, templates, and lesson sources

Tools and templates

Tools open in a new tab so you can keep your place here.

Sources and further reading

Explore the references behind this lesson.

O*NET OnLine — Human Resources Assistants, Except Payroll and Timekeeping
Source & access notes · checked 2026-10-01

Opened the occupational tasks, including preparation of new-employee orientation and maintenance of authorized personnel records. Role context does not grant real HR authority.

Access: Readable official webpage or PDF text opened with the web reader on 2026-10-01. No video playback, authenticated service or software operation is certified.

Reuse: Original fictional role, records, questions, data and worked practice; concepts paraphrased with attribution. No agency exercise or rubric copied.

U.S. OPM — Talent Management
Source & access notes · checked 2026-10-01

Read onboarding, skills-gap analysis and development sections. Federal organizational guidance is adapted conceptually to a fictional learning center, not claimed as universal law.

Access: Readable official webpage or PDF text opened with the web reader on 2026-10-01. No video playback, authenticated service or software operation is certified.

Reuse: Original fictional role, records, questions, data and worked practice; concepts paraphrased with attribution. No agency exercise or rubric copied.

U.S. OPM — DSS Onboarding Toolkit
Source & access notes · checked 2026-10-01

Opened the 14-page agency toolkit, including coordinator, supervisor, workspace readiness, first-day/week and follow-up roles. Historical agency-specific requirements are not imposed on the fictional case.

Access: Readable official webpage or PDF text opened with the web reader on 2026-10-01. No video playback, authenticated service or software operation is certified.

Reuse: Original fictional role, records, questions, data and worked practice; concepts paraphrased with attribution. No agency exercise or rubric copied.